What to Include in an Industrial Fabrication RFQ

October 2, 2026

A practical guide for obtaining accurate quotations

Requesting a quotation for industrial fabrication is more than sending a drawing and asking for a price. The quality of the information included in a request for quotation—RFQ—directly affects the accuracy of the proposal, the reliability of the schedule, and the number of clarifications required before work can begin.

Whether you need piping spools, tanks, structural steel, equipment platforms, ductwork, or modular rooms, providing complete technical and commercial information allows your fabrication partner to evaluate the work properly from the beginning.

At ECSAR, we review each project from an engineering, fabrication, logistics, and installation perspective. This helps identify potential issues before they affect cost or delivery.

1. Define the exact scope of work

Begin by clearly describing what you expect the contractor to provide.

Your RFQ should state whether the scope includes:

  • Engineering or drawing development
  • Material purchasing
  • Cutting, forming, welding, and assembly
  • Surface preparation and painting
  • Galvanizing or specialty coatings
  • Inspection and testing
  • Packaging and labeling
  • Transportation
  • Installation or construction management
  • Commissioning or final adjustments

A quotation can only be compared fairly when all bidders are pricing the same scope. If certain responsibilities are still undecided, identify them as optional items or request separate pricing.

2. Provide complete drawings and specifications

Drawings should be accompanied by the latest available specifications. Depending on the project, these may include:

  • General arrangement drawings
  • Fabrication or shop drawings
  • Isometric piping drawings
  • Structural details
  • Equipment connection drawings
  • Piping and instrumentation diagrams
  • Bills of materials
  • Design calculations
  • Applicable codes and standards
  • Welding procedures and inspection requirements

Always identify the drawing revision being used. Fabricating from outdated documents can lead to rework, schedule delays, or components that do not match the field conditions.

If final drawings are not yet available, provide preliminary information and identify what remains to be developed.

3. Identify materials and technical requirements

Material requirements should be as specific as possible. An RFQ may need to identify:

  • Material type and grade
  • Pipe diameter and wall thickness
  • Plate thickness
  • Structural profiles
  • Stainless steel or carbon steel requirements
  • Gaskets, flanges, valves, and specialty components
  • Coating or lining systems
  • Insulation requirements
  • Fastener grades and finishes

For tanks and process equipment, also include the intended service, operating temperature, pressure, fluid, volume, corrosion requirements, and required nozzles or connections.

When material specifications are incomplete, the contractor may need to include assumptions. Those assumptions should be stated clearly in the quotation so they can be reviewed before award.

4. Explain quality and inspection requirements

Quality requirements should be included before fabrication begins, not after the quotation has been submitted.

Specify whether the project requires:

  • Dimensional inspection
  • Visual weld inspection
  • Dye penetrant testing
  • Magnetic particle testing
  • Ultrasonic testing
  • Radiographic testing
  • Hydrostatic or pressure testing
  • Material certificates
  • Welding procedure qualifications
  • Welder qualifications
  • Inspection reports
  • Client or third-party hold points

These requirements influence labor, equipment, scheduling, documentation, and cost. If they are not defined in the RFQ, quotations may not be directly comparable.

5. Include quantities and delivery requirements

List the approximate quantities, dimensions, and expected delivery dates for each item. A useful RFQ may include:

  • Number of assemblies
  • Number of spools
  • Total weight
  • Overall dimensions
  • Required delivery sequence
  • Partial delivery requirements
  • Site receiving limitations
  • Packaging requirements
  • Final destination

Delivery sequence can be as important as total delivery date. For example, a project may require piping spools to arrive in installation order or structural components to be delivered according to the erection sequence.

Early logistics planning can also identify whether an assembly needs to be divided into smaller sections for transportation and field installation.

6. Describe the project location and site conditions

If installation or delivery is included, provide information about the project site:

  • Location
  • Access restrictions
  • Working hours
  • Available lifting equipment
  • Storage limitations
  • Required safety documentation
  • Site induction requirements
  • Local labor or licensing requirements
  • Restrictions on hot work, cranes, or transport
  • Whether field measurements are required

For export projects, include the destination country, customs requirements, shipping terms, required documentation, and packaging standards.

7. Separate required items from optional items

A clear RFQ distinguishes between mandatory scope and possible additions.

For example:

  • Base scope: fabrication of piping spools
  • Option 1: coating and painting
  • Option 2: transportation
  • Option 3: field installation
  • Option 4: additional inspection
  • Option 5: expedited production

This gives the client flexibility while allowing the contractor to price each element transparently.

8. State the commercial requirements

The RFQ should explain the commercial conditions expected from bidders, including:

  • Currency
  • Taxes and duties
  • Payment terms
  • Requested quotation validity
  • Expected start date
  • Required completion date
  • Warranty requirements
  • Retention or bonding requirements
  • Insurance requirements
  • Change-order procedures
  • Preferred Incoterms for international shipments

A technically complete quotation may still be difficult to evaluate if commercial conditions are not clearly defined.

9. Allow time for technical questions

Fabricators often identify important questions during their review. Give bidders a deadline for submitting clarifications and provide a date for issuing responses.

A structured clarification process helps ensure that every bidder receives the same information. It also creates a record of assumptions and decisions that can be referenced after the project is awarded.

A practical RFQ checklist

Before sending an industrial fabrication RFQ, confirm that you have included:

  • Clear scope of work
  • Latest drawing revisions
  • Quantities and dimensions
  • Material specifications
  • Applicable codes and standards
  • Welding and inspection requirements
  • Coating or finishing requirements
  • Delivery location and schedule
  • Packaging and transportation requirements
  • Site conditions, if installation is included
  • Commercial terms
  • Required quotation format
  • Deadline for questions and proposals

The better the information, the better the quotation

A complete RFQ helps everyone involved. The client receives a more accurate price and schedule, while the fabricator can plan materials, labor, equipment, inspection, and logistics with fewer unknowns.

At ECSAR, we support industrial projects from engineering review and material coordination through fabrication, delivery, and field support. Since 2002, our work has included industrial piping, tanks, ventilation systems, modular rooms, structural steel, miscellaneous metalwork, and integrated fabrication projects in Mexico and for export markets.

If you are preparing an industrial fabrication package, send us your drawings, specifications, quantities, delivery requirements, and project location. Our team can review the scope and help identify the information required to develop a practical quotation.

Contact ECSAR to discuss your next fabrication project.

‍

Get In Touch With Us

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
OUR OFFICEs
San Antonio
401 E. Sonterra Blvd, Suite 375
San Antonio, TX, 78258, USA

+1 (210) 510 4122
‍
Saltillo

Calzada Antonio Narro 3182 Saltillo, Coahuila, 25070, Mexico

+52 844 696 5363
WORKING HOURS
7:30AM - 6PM, Mon to Fri
CONTACT
sales@ecsar.net
+1 (210) 510 4122